Other Successfully Completed Projects

Project Year: 2019
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Maintenance Group Directorate

SCOPE

10 Pieces Column Maintenance and Repair Works

21 Pieces Drum Maintenance and Repair Works

2 Pieces Heater Maintenance and Repair Works

205 Pieces PSV-Orifice Maintenance and Repair Works

Project Year: 2017
Client:
Synpet Technology Co. Inc.

SCOPE

45 Staff / Month

Total: 58.000 Man-Hour Working (6 Months)

Project Year: 2015
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

Tank Hot Oil System Project Design

9.600 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2015
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

New Water Treatment Plant Equipment Installation Works

Pump Station and Injection System Installation and Construction Works

65.000 WDI (Dia-inches) Underground and Aboveground Steel Piping Fabrication and Erection

2.400 Meters HDPE Piping and Construction Works (Pipe Diameter: 500 mm)

64 Pieces Burner Maintenance and Piping Works

8.000 m3 Excavation and BackFilling Works

Project Year: 2015
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

3.500 WDI (Dia-inches) Stainless Steel Piping Fabrication and Erection

Project Year: 2014
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

44 Pieces Base Foundation Concrete Reinforcement Works

75 Ton Steel Column Reinforcement Works

Project Year: 2014
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

Fuel Gas Plant Equipment Installation Works

65 Tons of Drum, Equipment Installation and Construction Works

45.000 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2013
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE 

85 Tons Steel Platform Project Design, Fabrication and Erection Works

Project Year: 2013
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE

Tank Blasting and Painting Works

 

Project Year: 2013
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Maintenance Group Directorate

SCOPE

41 Pieces Heat Exchangers Maintenance and Repair Works

 

Project Year: 2012
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

27.500 WDI (Dia-inches) Piping Fabrication and Erection

55 Tons Steel Platform Project Design, Fabrication, Erection and Construction Works

Project Year: 2012
Client:
AYGAZ Co. Inc.

SCOPE

Tank Equipments Installation Works

24.000 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2011
Client:
EnerjiSA A.Ş. Co. Inc.

SCOPE 

Plant-wide Painting and Touch-Up Works

Project Year: 2011
Client:
AYGAZ Co. Inc.

SCOPE

New Sprinkler System and Hydrant Installation

1.200 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2011
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE 

850 Tons of Piping and Steel Structure Dismantling Works in Existing Old Facility

Project Year: 2011
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

Total: 890 Tons Tank Maintenance Replacement and Renovation Mechanic Works

2 Pieces Tank Steel Base Replacement (Tank Diameter: 55 Meters)

1 Piece Tank Steel Floating Roof Replacement (Tank Diameter: 55 Meters)

1 Piece Tank Steel Cone Roof Replacement (Tank Diameter: 55 Meters)

2 Pieces Tank Dome Roof Replacement (Tank Diameter: 24 Meters)

Project Year: 2010
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE 

Pump Station Modification Works

Pumps Installation and Pump Piping Works

Project Year: 2010
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Maintenance Group Directorate

SCOPE 

64 Pieces Heat Exchangers Maintenance and Repair Works

Project Year: 2010
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE 

Equipment Installation and Piping Works

Project Year: 2010
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Maintenance Group Directorate

SCOPE 

14 Pieces Column Maintenance and Repair Works

22 Pieces Drum Maintenance and Repair Works

Project Year: 2010
Client:
Aygaz Co. Inc.

SCOPE 

On 55 Concrete Foundations, Steel Pipe Bridge Project Design, Fabrication and Erection Works

42.500 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2010
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE

22 Pieces Concrete Foundation Construction Works

1.200 WDI (Dia-inches) Steel Piping Fabrication and Erection

Project Year: 2009
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE 

Internal Plant Piping, Maintenance and Renovation Works

Project Year: 2008
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

125 Tons Steel Structure Project Design, Fabrication and Erection

Steel Structure Construction Works

2.200 m2 Sandwich Panel Installation

Project Year: 2007
Client:
Shell & Turcas Petroleum Co. Inc.

SCOPE

9.000 WDI (Dia-inches) Piping Fabrication and Erection

Project Year: 2007
Client:
Korfez Chamber of Commerce

KAPSAM 

135 Tons Steel Structure Project Design, Fabrication and Erection

Total: 2000 m2 Steel Structure Construction Works

2.000 m2 Sandwich Panel Installation

Project Year: 2006
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

25.000 WDI (Dia-inches) Piping Fabrication and Erection

Project Year: 2006
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

180.000 WDI (Dia-inches) Piping Fabrication and Erection

50 Tons Steel Pipe Bridge Project Design, Fabrication and Erection

Reinforcement and Construction Works

Project Year: 2006
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

10.000 m2 Sandwich Panel Installation

10.000 m2 Trapezoidal Sheet Metal Installation

Project Year: 2005
Client:
Nuh Cement Co. Inc.

SCOPE

2.400 WDI (Dia-inches) Piping Fabrication and Erection

Project Year: 2005
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

35 Pieces Tank Foam Extinguisher and Sprinkler System Installation Works

68.000 WDI (Dia-inches) Piping Fabrication and Erection

Project Year: 2003
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

75 Tons Equipment Installation and Piping Erection Works

Project Year: 2003
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

26 Pieces Filling Arm Replacement and Improvement Works

Project Year: 2003
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

9.800 WDI (Dia-inches) Piping Fabrication and Erection

Project Year: 2002
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Maintenance Group Directorate

SCOPE

64 Pieces Heat Exchangers Maintenance and Repair Works 

Project Year: 2001
Client:
TUPRAS (Turkish Petroleum Refineries Co. Inc.) - Project Investments Directorate

SCOPE

12.500 WDI (Dia-inches) Piping Fabrication and Erection

38 Tons Steel Platform Project Design, Fabrication, Erection and Construction Works